GPK1 well
Description
GPK1 was the first well drilled for geothermal purposes at Soultz-sous-Forêts. The well was first drilled in 1987. It reached 2000 m and the temperature at the bottom hole was 140°C. Several hydraulic injections have been done associated with tracer tests and temperature and flow logs.
In order to get deeper information, the GPK1 well was deepened to 3600 m in 1992. The downhole temperature reached 160°C.
Location GPK1 WGS84: Latitude: 48.93525543 | 48° 56' 6'' N Longitude: 7.86535117 | 7° 51' 55'' E
| BRGM information about GPK1 well at infoterre |
| Data request form |
| Recorded data: see Dezayes et al., 2010 (p.134-142) |
This ressource is in following collection(s)
https://doi.org/10.25577/SSFS1993
https://doi.org/10.25577/SSFS1995
Stakeholders
Creator(s)
GEIE - Exploitation Minière de la Chaleur
Rights Holder(s)
Location
Temporal coverage
1993
Subjects
Keywords
How to cite
« Infoterre Fiche Données - Dossier du sous-sol - BSS000QJPC ». s. d. Consulté le 28 février 2018. http://ficheinfoterre.brgm.fr/InfoterreFiche/ficheBss.action?id=BSS000QJPC.
License
Except where otherwise noted, content for this ressource is licensed under a Creative Commons Attribution 4.0 International license.
Ressource last modified on May 28, 2026